VH-SIK Construction Log
Date Progress Time Taken
3 November 03 Finished cutting outer envelope patterns 7 hours
8 November 03 Finished cutting panels 16 hours
21 November 03 Rip  panels completed 4 hours
23 November 03 Individual gores completed (horizontal seams) 26 hours
26 November 03 Gores joined and vertical load tapes attached 14 hours
30 November 03 Top & bottom rim tapes, horizontal rip stoppers, flying wires

Registration & Experimental marks

6 hours
1 December 03 Installed hook & loop fasteners for rip panel

Cut panels A, C - H for inner envelope

8 hours
2 December 03 Envelope bag for outer envelope

Installed ID plate on outer envelope

4 1/2 hours
4 December 03 Cut 'B' panels for inner envelope

Joined panels H,G,F,E for all 16 gores

7 hours
5 December 03 Joined panels D, C, B for all 16 gores 4 hours
6 December 03 Completed individual gores and joined 10 of 16 7 hours
7 December 03 Joined remaining 6 gores together - closing seam, load tapes and deflation panel installation remain 4 hours
8 December 03 Applied vertical load tapes to inner skin, installed top panel including velcro rip, completed closing seam. Manufactured flying wires from vectran cord 7 hours
9 December 03 First Inflation of both envelopes completed 3 hours

Back to Mylar Magic